Do We Need a Permit to Film in Melbourne?

By Matt Smolen · Last reviewed

In Short

  • Ask your production company who manages each location. A council, Parks Victoria or a private owner decides, and Parks Victoria treats business video as commercial filming.
  • Start the permit as soon as the place and date are agreed. Its lead time adds to a typical project's 2 to 4 weeks.
  • Ask for any permit fees as their own lines on the quote and invoice. Ask for the time to prepare the application to be costed at quote stage.
  • Before you sign, ask who lodges the application and whose public liability insurance goes on it.

Parks Victoria needs at least 10 business days to process a filming permit, and 20 if there's a drone. Our shoots are usually booked about two weeks ahead. So a permit's lead time can match or exceed the two weeks we usually book ahead, and a drone adds more.

This guide sets out what Parks Victoria, VicScreen, Victoria Police and the council listings say. It covers when business video needs a permit, how long one takes and what it adds to a quote.

It isn't legal advice. Fees and rules change, so check the current rules with the body that manages your location.

Who Decides Depends on Who Manages the Land

There is no single Melbourne filming permit. The permit comes from whoever manages each place you film.

Victoria's Filming Approval Act 2014 sets standard processes for filming on public land. The Premier's 2015 announcement says the Act requires all councils and public agencies to adopt standard processes for filming applications. Standard processes don't mean the same rules everywhere, as the next sections show.

Streets, footpaths and council parks. The council for that area decides. Boroondara, for example, lists parks, footpaths, nature strips, public car parks and roads as council-controlled land. For the City of Melbourne, the Australian Government's business.gov.au listing links to the council's own page.

State and national parks. Parks Victoria decides, and its filming permit page says shoots across several land managers may need other permits too. It names Albert Park as one of its high-use parks.

Roads and other Crown land. Victoria Police's film page says filming on a public road needs a permit from its manager. That could be, for example, the council, the Department of Transport and Planning or a tollway operator.

Other Crown land has its own manager. VicScreen's Film Friendly Victoria page links to road, park and DEECA filming pages. Check the current rules, and ask your production company which one applies.

Places with their own owner. Some sites run their own approval. Melbourne Airport asks for an application before any filming, at least eight business days ahead, or $500 plus GST extra. Its page says commercial filming won't be permitted from 1 December 2026 to 31 January 2027, so check the current rules there.

Private property. The standard processes are for public land. On private property the owner or manager sets the rules. What a shopping centre or a secure building expects is in what happens in pre-production.

Ask your production company for one line per location: who manages it, whether it needs a permit, and the date the application goes in.

What Counts as Needing a Permit

Parks Victoria's page lists advertising and promotions as commercial filming, and commercial filming is what its permits are about.

Parks Victoria. A permit is typically needed for filming or photography done as a trade or business, and its page lists advertising and promotions. Hobby photographers with basic equipment and people filming for personal use generally don't need one.

All drone filming on its land needs a permit, and Parks Victoria asks for CASA-licensed pilots. The pilot rules are on CASA's drone page.

City of Melbourne. The listing says commercial filming in a public place, such as roads, beaches, gardens or zoos, needs a permit. Its low impact category means six people or fewer, one camera, one tripod and handheld sound, with public paths kept clear. Check the current rules.

Ask the council whether your shoot counts as low impact, and whether it needs notice or a permit. If the answer is unclear, ask for it in writing before you book.

The listing says medium and high impact shoots add paperwork, such as a running sheet, site plans and a risk assessment.

Other councils set their own lines. Boroondara says you don't need a filming permit if you use a hand-held camera. Arts Law notes that councils treat filming differently. If your video moves across suburbs, each council can answer differently.

Applying isn't approving. Parks Victoria says an application isn't an approval, so don't announce a location until the permit is issued. Ask your production company for a fallback location, so the shoot has somewhere to go if a permit is refused.

Insurance for the Permit

Expect to hand over a public liability insurance certificate with the application.

The land manager sets the minimum. Parks Victoria requires at least $20 million, notes its own interest on the policy and doesn't accept a certificate for less.

Boroondara asks for $20 million for motion picture filming and $5 million for commercial stills. Melbourne Airport asks for $20 million, plus a current workers compensation certificate.

For the City of Melbourne, the listing asks for a copy of public liability insurance with medium and high impact filming. Ask the council for its current minimum and who the policy names.

Drone operators need their own certificate too: Parks Victoria asks for $20 million public liability including aviation cover, naming the drone model. The drone guide covers the rest.

When we lodge a permit, we use our own insurance. Our public liability cover meets Parks Victoria's $20 million, which is a typical amount for a production company. Ask any production company to confirm in writing that its cover meets the amount your locations ask for.

How Long a Permit Adds to Your Schedule

Plan the application date backwards from the shoot, and count the days from the day the paperwork is complete.

  • Parks Victoria: at least 10 business days after it has all your documents. It's 20 with a drone, and it won't accept applications with less.
  • City of Melbourne: ask the council how long yours will take.
  • Boroondara: at least 10 business days before filming. It also asks for written notice to residents and traders 7 days before you apply. Check the council's current rules for any other notice it asks for.
  • Victoria Police: it recommends notification, often a permit requirement, when the public may see or hear a shoot and it may cause alarm. Examples are firearms, special effects or large crowds. Allow at least two business days.

Those are minimums, and a complex application can take longer.

A permit's lead time adds to our 2 to 4 weeks from brief to delivery. In many cases we flag it up front.

How long the rest of the job takes is in how long does it take to make a corporate video.

What a Permit Adds to Your Quote, and Who Applies

We lodge permits for you. A good production company does the same, on behalf of you and the production.

We apply to the councils, agencies and location owners involved. We prepare the application, lodge it and handle any questions the land manager sends back. That time is part of pre-production, so it's costed at quote stage.

Examples of our location work are on video production in Melbourne.

Any permit fees are separate. They're itemised as their own lines on the quote and invoice, so you see what the land manager charges.

Some locations add parking charges. Each outside cost should say whether it's in the total.

Parks Victoria fees depend on how complex the shoot is, and complex or high-impact shoots can cost more. The permit isn't confirmed until you pay.

If you cancel, Parks Victoria refunds 100% with 30 or more days' notice. It's 85% from 8 to 30 days, 50% from 4 to 7 days, and nothing in the last 3 days. Ask how a late date change is handled.

The City of Melbourne's listing shows an application fee, a unit base fee and a fee for how long you film. Fees change each financial year, so check the council's current rules.

Parking bays can cost extra. Boroondara, for example, lists a separate per-bay, per-day fee. Ask the council for the suburb you film in.

Before you sign, ask your production company who lodges the application and whose insurance goes on it. How to read outside costs on a quote is in what goes into a video production quote.

If a permit adds weeks and fees, ask your production company whether a space you already have access to works for the shot. The owner has to agree, and your production company can say whether anything else applies.

What if we film without a permit?

Boroondara's page says penalties may apply when you film on council land without one. Arts Law adds that setting up a tripod on a busy street and refusing to move when asked could be an obstruction offence. The body that manages the location confirms the consequences.

Do we need to tell the police?

Possibly. Victoria Police recommends notification, often a permit requirement, when the public may see or hear a shoot and it may cause alarm. Examples are firearms, special effects or large crowds. The City of Melbourne listing names weapons, special effects, drones, traffic management and scenes that may cause public concern. Notifying police isn't approval from the land or road manager.

Does a permit mean a bigger, slower project?

A permit typically adds a bit of time, though that isn't true of every job. Projects that need a permit often have a larger crew or talent, which need a longer lead time anyway. A small shoot can still need a permit, and its lead time adds to the schedule too.